Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DARTMOUTH- CORRIDOR IMPROVEMENTS ON DARTMOUTH STREET AND PROSPECT STREET
Work on this project consists of corridor improvements on Dartmouth Street from Howland Road to Middle Street/Prospect Street and extends on Prospect Street to Elm Street. This is the third and final phase of improvements on Dartmouth Street, which consists of pavement rehabilitation and Bicycle/Pedestrian accommodation. In addition, drainage, curbing, pavement and signage need improvement. Improvements at the intersection at Prospect and Middle Streets are being considered, including the possible construction of a roundabout.
Location:
  • Town of Dartmouth
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $3,707,058.85
    Estimated Total Federal Participating Construction Cost: $4,168,046.20
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Rejected (as of 04/02/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $4,668,212 - $2,800,000 CMAQ/$1,868,212 STBG d) EC Score 42 of 100; h) Project Proponent - Dartmouth; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,494,569.60
    State Cost: $373,642.40
    Total Cost: $1,868,212.00

    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: DARTMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $4,668,212 - $2,800,000 CMAQ/$1,868,212 STBG d) EC Score 42 of 100; h) Project Proponent - Dartmouth; i) Status Pre 25%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,240,000.00
    State Cost: $560,000.00
    Total Cost: $2,800,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/20/2016
    Project Initiation Form PIF Entered 07/25/2016
    Project Initiation Form PRC Submitted 09/14/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management
    25% Design 25% Package Received 10/11/2019
    25% Design 25% Package Comments to DE 01/15/2020
    25% Design 25% Package Rejected 04/02/2020