Project Description:
DEDHAM- RECONSTRUCTION & RELATED WORK OF BRIDGE STREET (ROUTE 109) AND AMES STREET
Sidewalks and wheelchair ramps will be provided throughout the corridor, roadway pavement will be reconstructed with five-to-six foot wide bicycle lanes and eleven-to-twelve foot wide travel lanes and the existing drainage system will be rehabilitated. The project also includes reconstructing the Bridge Street and Ames Street intersection with improved geometry, new traffic signal equipment and full pedestrian accommodation. Work also includes the removal of an existing pedestrian signal and the installation of Rectangular Rapid Flashing Beacons (RRFB) at two locations. The work includes full depth hot mix asphalt pavement, milling and overlay, drainage improvements, fence and guardrail installation, new granite curbing, concrete sidewalks, retaining wall construction, landscaping, traffic signing, traffic control management, and other street improvements.
Location:
  • Town of Dedham
  • Construction Begins: Spring 2020
    Resident Engineer: Fritz Dubuisson
    Construction Bid Price: $6,637,359.50
    District: District 6

    Contracts (2) Progress
    # 109675 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Sections of Ames and Bridge Streets (Route 109) Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/21/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/20/2016
    Project Initiation Form PIF Entered 05/20/2016
    Project Initiation Form PRC Submitted 05/20/2016
    Project Review Committee PRC Approved 05/20/2016
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 03/19/2019
    100% Design 100% Package Comments to DE 04/22/2019
    25% Design 25% Package Received 05/02/2016
    25% Design 25% Package Comments to DE 08/30/2016
    25% Design 25% Package Approved 07/15/2016
    25% Design Design Public Hearing 02/07/2018
    75% Design 75% Package Received 07/03/2018
    75% Design 75% Package Comments to DE 09/10/2018
    Final Design PS&E Received 06/25/2019
    Final Design PS&E to FAPRO 08/30/2019
    Final Design PS&E Received - Resub 1 08/27/2019