Project Description:
TRURO- BICYCLE ACCOMMODATION IMPROVEMENT ON ROUTE 6 FROM SOUTH HIGHLAND ROAD TO SOUTH HOLLOW ROAD (PHASE 2)
Work on this project consists of milling and overlay of the roadway, installing pavement markings for bicycle lanes and signage along Route 6 in the Town of Truro from South Highland Road to Shore Road. In addition, improvements are proposed at the Route 6/Shore Road intersection including modification of the crossing. Also, the Route 6 pavement markings will be reconfigured between Shore Road and South Hollow Road, moving the 2 to 4 lane shift cross section closer to South Hollow Road located to the North.
Location:
  • Town of Truro
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Michael King
    Construction Bid Price: $896,867.50
    District: District 5

    Contracts (1) Progress
    # 105479 -- Construction Contract
    Bicycle Improvements, Resurfacing and Related Work along a Section of Route 6 (Phase II) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/11/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/20/2016
    Project Initiation Form PIF Entered 05/20/2016
    Project Initiation Form PRC Submitted 08/12/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 08/11/2018
    Project Management
    100% Design 100% Package Received 07/16/2018
    25% Design 25% Package Received 12/14/2017
    25% Design 25% Package Comments to DE 01/26/2018
    75% Design 75% Package Received 12/14/2017
    75% Design 75% Package Comments to DE 01/26/2018
    Final Design PS&E Received 07/16/2018
    Final Design PS&E to FAPRO 07/30/2018