Project Description:
DISTRICT 3- CLEAN AND PAINT STRUCTURAL STEEL BRIDGES ON I-190 AND I-290
This project will consist of full cleaning and painting of Bridge No. W-24-017 (BIN = 1X2) in West Boylston and Bridge No. W-44-112 (BIN = 216) and W-44-118 (BIN = 1XD) in Worcester.
Location:
Construction Begins: Winter 2020/2021
Resident Engineer: Kevin Troy
Construction Bid Price: $3,635,907.50
District: District 3

Contracts (1) Progress
# 113678 -- Construction Contract
Structural Steel Cleaning, Painting and Repairs to 5 Bridges on Interstates 190 and 290 Completed

Bridges

Contract Dates
Notice to Proceed: 02/18/2021
Contract Information
Project Designer: In-House Boston
Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 05/23/2016
Project Initiation Form PIF Entered 05/23/2016
Project Initiation Form PRC Submitted 05/23/2016
Project Review Committee PRC Approved 06/09/2016
Project Status Advertised 12/19/2020
Project Management
100% Design 100% Package Received 09/24/2020
Final Design PS&E Received 10/21/2020
Final Design PS&E Received - Resub 1 11/06/2020