Project Description: |
DISTRICT 5- SYSTEMATIC BRIDGE PRESERVATION ALONG THE I-95 CORRIDOR
This project is to perform painting of the bridges on the I-95 corridor.
|
Location: | |
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | M. Ali Jalinous |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|