Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- SYSTEMATIC BRIDGE PRESERVATION ALONG THE I-95 CORRIDOR
This project is to perform painting of the bridges on the I-95 corridor.
Location:
Construction Begins: Spring 2020
Resident Engineer: Eric Borman
Construction Bid Price: $2,595,768.00
District: District 5

Contracts (1) Progress
# 110153 -- Construction Contract
Bridge Deck and Joint Repairs and Related Work (Including Painting) on 7 Bridges along Interstate 95 Completed

Bridges

Contract Dates
Notice to Proceed: 05/08/2020
Contract Information
Project Designer: In-House Boston
Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 05/25/2016
Project Initiation Form PIF Entered 05/25/2016
Project Initiation Form PRC Submitted 05/25/2016
Project Review Committee PRC Approved 06/09/2016
Project Status Advertised 11/16/2019
Project Management
100% Design 100% Package Received 09/10/2019
100% Design 100% Package Comments to DE 09/25/2019
75% Design 75% Package Received 07/29/2019
75% Design 75% Package Comments to DE 09/03/2019
Final Design PS&E Received 09/30/2019
Final Design PS&E Received - Resub 1 10/23/2019