DISTRICT 5- SYSTEMATIC BRIDGE PRESERVATION ALONG THE I-195 CORRIDOR
This project is to perform painting of the bridges on the I-195 corridor.
Location:
Construction Begins: Winter 2020/2021
Resident Engineer: Rajat Gogoi
Construction Bid Price: $1,188,192.50
District: District 5

Contracts (1) Progress
# 113451 -- Construction Contract
Bridge Painting and Related Work (Including Structural Steel Repairs) Br. Nos. R-04-017 and S-08-012 over Interstate 195 Completed

Bridges

Contract Dates
Notice to Proceed: 01/22/2021
Contract Information
Project Designer: In-House Boston
Funding Source: FED. AID. ACCELERATED BRIDGE
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 05/25/2016
Project Initiation Form PIF Entered 05/25/2016
Project Initiation Form PRC Submitted 05/25/2016
Project Review Committee PRC Approved 06/09/2016
Project Status Advertised 11/07/2020
Project Management
100% Design 100% Package Received 07/20/2020
100% Design 100% Package Comments to DE 08/26/2020
Final Design PS&E Received 09/10/2020
Final Design PS&E Received - Resub 1 10/02/2020