Project Description:
ATTLEBORO- STORMWATER IMPROVEMENTS ALONG INTERSTATE 95
Stormwater Improvements along I-95 in Attleboro between the interchanges of I-95 and I-295 and I-95 and Route 122 to treat stormwater discharges to Fourmile Brook and Ten Mile River.
Location:
  • City of Attleboro
  • Construction Begins: Summer 2021
    Resident Engineer: Roderick Jackson
    Construction Bid Price: $952,629.80
    District: District 5
    Current Status: Current Operations: Contractor is currently idle. Future Operations: Contractor scheduled to finish punch list items. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. (as of 05/09/2023)

    Contracts (3) Progress
    # 114577 -- Construction Contract
    Stormwater Improvements along a Section of Interstate 95 Completed
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/10/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Current Operations: Contractor is currently idle. Future Operations: Contractor scheduled to finish punch list items. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2016
    Project Initiation Form PIF Entered 05/27/2016
    Project Initiation Form PRC Submitted 05/27/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 05/15/2021
    Project Management
    100% Design 100% Package Received 01/29/2021
    25% Design 25% Package Received 05/18/2020
    75% Design 75% Package Received 10/01/2020
    Final Design PS&E Received 01/29/2021
    Final Design PS&E to FAPRO 04/26/2021