Project Description:
CANTON- NORWOOD- STORMWATER IMPROVEMENTS ALONG ROUTE 1 & I-95
Stormwater Improvements to treat discharges from Route 1, I-95 and Route 1A to the Neponset River and an Unnamed Tributary.
Location:
  • Town of Canton
  • Town of Norwood
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2022
    Project Manager: Hung Pham
    Estimated Total Contract Cost: $450,855.65
    Estimated Total Federal Participating Construction Cost: $501,103.03
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 5
    Current Status: 100% Package Received (as of 03/22/2021 )

    Contracts (2) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CANTON
    FOXBOROUGH
    NORWOOD
    SHARON
    WALPOLE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $407,103.20
    State Cost: $101,775.80
    Total Cost: $508,879.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2016
    Project Initiation Form PIF Entered 05/27/2016
    Project Initiation Form PRC Submitted 05/27/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Management
    100% Design 100% Package Received 03/22/2021
    25% Design 25% Package Received 12/03/2019
    25% Design 25% Package Comments to DE 03/11/2020
    75% Design 75% Package Received 03/22/2021