Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHICOPEE- WEST SPRINGFIELD- HIGHWAY LIGHTING UPGRADE ON I-91
The project shall consist of lighting pole improvements to the I-91 Main line, beginning at the east end of the Connecticut River Bridge in Chicopee and ending 2000 feet east of the Brush Hill Avenue bridge in West Springfield. The project shall include, but not be limited to, repair and replacement of bridge barrier and construction of barrier bump outs to accommodate new light pole bases, replacement of damaged lighting poles and appurtenances, installation of new lighting poles, luminaries, load center modifications, conduit, wire, and associated new electrical equipment, and appurtenances as noted on the Contract Drawings.
Location:
  • City of Chicopee
  • Town of West Springfield
  • Construction Begins: Summer 2019
    Resident Engineer: Aziz Bensoum
    Construction Bid Price: $5,934,294.70
    District: District 2

    Contracts (2) Progress
    # 106579 -- Construction Contract
    Highway Lighting Improvements and Related Work along a Section of Interstate 91 Completed
    # 72436 -- Design -- Traffic Signing/Signals
    Work will consist of providing engineering services in connection with the design and modifications to the statewide highway lighting system. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/18/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2016
    Project Initiation Form PIF Entered 05/27/2016
    Project Initiation Form PRC Submitted 06/01/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 12/08/2018
    Project Management
    75% Design 75% Package Received 12/23/2016
    Final Design PS&E Received 06/12/2017
    Final Design PS&E to FAPRO 08/07/2018
    Final Design PS&E Received - Resub 2 03/28/2019