Project Description:
FALL RIVER- SOMERSET- STORMWATER IMPROVEMENTS ALONG I-195 AND ROUTE 79
Stormwater Improvements at various locations in Fall River and Somerset to treat roadway discharges into the Taunton River and Mount Hope Bay.
Location:
  • City of Fall River
  • Town of Somerset
  • Construction Begins: Autumn 2019
    Resident Engineer: Rajat Gogoi
    Construction Bid Price: $1,281,282.11
    District: District 5

    Contracts (1) Progress
    # 108463 -- Construction Contract
    Stormwater Drainage Improvements and Related Work along Section of Routes 24 & 79 and Interstate 195 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/22/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/27/2016
    Project Initiation Form PIF Entered 05/27/2016
    Project Initiation Form PRC Submitted 05/27/2016
    Project Review Committee PRC Tabled 06/09/2016
    Project Review Committee PRC Approved 07/21/2017
    Project Status Advertised 06/29/2019
    Project Management
    100% Design 100% Package Received 03/08/2019
    25% Design 25% Package Received 11/19/2018
    75% Design 75% Package Received 03/08/2019
    Final Design PS&E Received 05/24/2019
    Final Design PS&E to FAPRO 06/17/2019