DUNSTABLE- IMPROVEMENTS ON MAIN STREET (ROUTE 113), FROM PLEASANT STREET TO 750 FT EAST OF WESTFORD STREET
The proposed improvements include roadway rehabilitation, minor widening for improved bike accommodation, construction of sidewalk along one side of the roadway, replacing a stone box culvert and reconstruction of a stone retaining wall. Additional work includes drainage improvements, guardrail replacement, and sign and pavement marking upgrades.
Location:
  • Town of Dunstable
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Patrick Marion
    Construction Bid Price: $3,807,861.00
    District: District 3

    Contracts (1) Progress
    # 116295 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Main Street (Route 113) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/10/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/31/2016
    Project Initiation Form PIF Entered 05/31/2016
    Project Initiation Form PRC Submitted 06/03/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 02/16/2021
    100% Design 100% Package Comments to DE 03/16/2021
    25% Design 25% Package Received 12/20/2017
    25% Design 25% Package Comments to DE 04/02/2018
    25% Design Design Public Hearing 06/17/2019
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Rejected 07/17/2020
    75% Design 75% Package Received - Resub 1 07/20/2020
    Final Design PS&E Received 07/02/2021
    Final Design PS&E Received - Resub 1 08/09/2021