Project Description:
DISTRICT 5- ADA RETROFITS AT VARIOUS LOCATIONS
This contract is for upgrading state-owned wheelchair ramps at various locations throughout the district to achieve compliance with the Americans with Disabilities Act and the Commonwealth's Architectural Access Board regulations under the MassDOT Transition Plan.
Location:
Construction Begins: Autumn 2021
Resident Engineer: Roderick Jackson
Construction Bid Price: $1,054,293.00
District: District 5

Contracts (3) Progress
# 115769 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final
# 116249 -- Construction Contract
Sidewalk and ADA Improvements at Various Locations Completed
# 77866 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/15/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/01/2016
    Project Initiation Form PIF Entered 06/01/2016
    Project Initiation Form PRC Submitted 06/01/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/04/2021
    Project Management
    100% Design 100% Package Received 08/14/2020
    100% Design 100% Package Comments to DE 09/21/2020
    25% Design 25% Package Received 03/02/2020
    25% Design 25% Package Received 03/02/2020
    75% Design 75% Package Received 03/02/2020
    75% Design 75% Package Comments to DE 05/13/2020
    Final Design PS&E Received 08/06/2021
    Final Design PS&E Received - Resub 1 08/20/2021
    Consultant Contract Process NTP Issued 10/24/2018