BRAINTREE- HIGHWAY LIGHTING IMPROVEMENTS AT I-93/ROUTE 3 INTERCHANGE
This project will replace and upgrade the existing highway lighting at the I-93/Route 3 interchange (Braintree Split) in Braintree.
Location:
  • Town of Braintree
  • Construction Begins: Autumn 2019
    Resident Engineer: Derek Coble
    Construction Bid Price: $4,747,217.00
    District: District 6

    Contracts (2) Progress
    # 108586 -- Construction Contract
    Highway Lighting Repairs and Improvements at Interstate 93 and the Route 3 Interchange (Braintree Split) Completed
    # 72503 -- Design -- Traffic Signing/Signals
    Work will consist of providing engineering services in connection with the design and modifications to the statewide highway lighting systems. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/20/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/02/2016
    Project Initiation Form PIF Entered 06/02/2016
    Project Initiation Form PRC Submitted 06/02/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 07/06/2019
    Project Management
    100% Design 100% Package Received 03/08/2019
    25% Design 25% Package Received 02/23/2018
    25% Design 25% Package Comments to DE 03/23/2018
    75% Design 75% Package Received 03/08/2019
    Final Design PS&E Received 06/04/2019
    Final Design PS&E to FAPRO 06/14/2019