Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- WESTWOOD- STEEL SUPERSTRUCTURE CLEANING (FULL REMOVAL) AND PAINTING OF 2 BRIDGES: B-16-118 & W-31-006
Location:
  • City of Boston
  • Town of Westwood
  • Construction Begins: Winter 2022/2023
    Resident Engineer: JoaoPaulo De Pina
    Construction Bid Price: $1,927,470.00
    District: District 6

    Contracts (1) Progress
    # 120831 -- Construction Contract
    Structural Steel Cleaning, Painting, and Repairs to Br. Nos. B-16-118 & W-31-006 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/26/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2016
    Project Initiation Form PIF Entered 06/06/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 11/26/2022
    Project Management
    100% Design 100% Package Received 08/04/2022
    100% Design 100% Package Comments to DE 09/08/2022
    Final Design PS&E Received 09/22/2022
    Final Design PS&E to FAPRO 11/10/2022