Project Description:
NEWTON- STEEL SUPERSTRUCTURE CLEANING (FULL REMOVAL) AND PAINTING OF N-12-055
Location:
  • City of Newton
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Christopher Ray
    Construction Bid Price: $1,137,023.50
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6

    Contracts (1) Progress
    # 113644 -- Construction Contract
    Structural Steel Cleaning, Painting and Repairs Br. No. N-12-055 Washington Street over Interstate 95. 2% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 02/10/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NEWTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $1,846,400.00
    State Cost: $461,600.00
    Total Cost: $2,308,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2016
    Project Initiation Form PIF Entered 06/06/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 12/12/2020
    Project Management
    100% Design 100% Package Received 09/23/2020
    100% Design 100% Package Comments to DE 10/20/2020
    25% Design 25% Package Received 02/21/2018
    Final Design PS&E Received 10/26/2020
    Final Design PS&E Received - Resub 1 11/13/2020