Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
RANDOLPH- QUINCY- REPLACEMENT & REHABILITATION OF HIGHWAY LIGHTING SYSTEM AT I-93/ROUTE 24
Location:
  • City of Quincy
  • Town of Randolph
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2022
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $7,032,267.18
    Estimated Total Federal Participating Construction Cost: $7,247,922.06
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 07/16/2022 )

    Contracts (2) Progress
    # 72503 -- Design -- Traffic Signing/Signals
    Work will consist of providing engineering services in connection with the design and modifications to the statewide highway lighting systems. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    RANDOLPH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Added via STIP Action 9
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,798,337.60
    State Cost: $1,449,584.40
    Total Cost: $7,247,922.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/06/2016
    Project Initiation Form PIF Entered 06/06/2016
    Project Initiation Form PRC Submitted 06/06/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 07/16/2022
    Project Management
    100% Design 100% Package Received 02/13/2020
    100% Design 100% Package Comments to DE 03/20/2020
    100% Design 100% Package Received - Resub 1 07/16/2021
    25% Design 25% Package Received 11/19/2019
    25% Design 25% Package Comments to DE 12/20/2019
    75% Design 75% Package Received 02/13/2020
    75% Design 75% Package Comments to DE 03/20/2020
    Final Design PS&E Received 04/25/2022
    Final Design PS&E to FAPRO 06/27/2022
    Consultant Contract Process NTP Issued 07/29/2019