ATHOL- BRIDGE REPLACEMENT, A-15-008, CRESCENT STREET OVER MILLERS RIVER
The work to be done at the Crescent Street Bridge under this Contract involves the replacement of the existing bridge structure carrying Crescent Street over Millers River at the same location and the reconstruction of a portion of each approach. The existing single-span bridge will be replaced with a new single-span bridge of the same span length. Work also includes full depth pavement reconstruction in both approaches, drainage improvements, sidewalk reconstruction, and utility installations and relocations.
Location:
  • Town of Athol
  • Construction Begins: Summer 2019
    Resident Engineer: Matthew Minihan
    Construction Bid Price: $4,259,499.25
    District: District 2

    Contracts (2) Progress
    # 107113 -- Construction Contract
    Bridge Replacement Br. No. A-15-008 (Pre-stressed Box Beams) Crescent Street over Millers River Completed
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/14/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/06/2016
    Project Initiation Form PIF Entered 06/06/2016
    Project Initiation Form PRC Submitted 06/06/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 02/23/2019
    Project Management
    100% Design 100% Package Received 12/05/2018
    100% Design 100% Package Comments to DE 01/07/2019
    25% Design 25% Package Received 01/08/2018
    25% Design 25% Package Comments to DE 03/05/2018
    25% Design 25% Package Approved 05/17/2018
    25% Design Design Public Hearing 04/26/2018
    75% Design 75% Package Received 08/06/2018
    75% Design 75% Package Comments to DE 10/04/2018
    Final Design PS&E Received 02/01/2019
    Final Design PS&E to FAPRO 02/11/2019