Project Description: |
BOSTON- BRIDGE SUBSTRUCTURE REPAIRS, B-16-179, AUSTIN STREET OVER I-93 RAMPS, MBTA COMMUTER RAIL AND ORANGE LINE
This is a bridge repair project; mill and pave the Gilmore bridge, deck joint replacements, deck repairs, beam end repairs, steel cleaning and painting, and substructure repairs.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Alyson Bedard![]() |
Estimated Total Contract Cost: | $16,665,000.00 |
Estimated Total Federal Participating Construction Cost: | $17,422,500.00 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|