Project Description:
HARWICH- BRIDGE REPLACEMENT, H-10-019, AZALEA DRIVE OVER HERRING RIVER
Location:
  • Town of Harwich
  • Construction Begins: Autumn 2022
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $3,985,137.00
    District: District 5
    Current Status: Current Proiect Status: The confractor has completed all physical work. The contractor is required to submit outstanding paperwork to finalize this project. Scheduled work hours are Monday through Friday, 9:00 AM to 3:00 PM. Expect periodic lane closures and restrictions. (as of 10/17/2024)

    Contracts (2) Progress
    # 120084 -- Construction Contract
    Bridge Replacement Br. No. H-10-019 (Pre-stressed Concrete Box Beams) Azalea Drive over Herring River Completed
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/01/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Current Proiect Status: The confractor has completed all physical work. The contractor is required to submit outstanding paperwork to finalize this project. Scheduled work hours are Monday through Friday, 9:00 AM to 3:00 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 08/27/2022
    Project Management
    100% Design 100% Package Received 09/20/2021
    25% Design 25% Package Received 10/01/2019
    25% Design 25% Package Comments to DE 11/11/2019
    75% Design 75% Package Received 05/13/2021
    Final Design PS&E Received 12/13/2021
    Final Design PS&E to FAPRO 08/15/2022
    Final Design PS&E Received - Resub 1 05/05/2022
    Final Design PS&E Received - Resub 2 07/19/2022