Project Description: |
HARWICH- BRIDGE REPLACEMENT, H-10-019, AZALEA DRIVE OVER HERRING RIVER
|
Location: |
|
Construction Begins: | Autumn 2022 |
Resident Engineer: | Dylan Hipolito |
Construction Bid Price: | $3,985,137.00 |
District: | District 5 |
Current Status: | The temporary pedestrian bridge is now open to the public and it will stay in place until the new road bridge has been complete. The contractor has completed pouring the concrete bridge deck and the abutment end diaphragms. On-going work consists of tying in the rest of the new 12-inch water main and pressure testing. Normal work hours are Monday through Friday, 9:00 AM to 3:00 PM. Expect periodic lane closures and restrictions. (as of 04/11/2024) |
|