Project Description:
REHOBOTH- BRIDGE REPLACEMENT, R-04-004, REED STREET OVER PALMER RIVER
Location:
  • Town of Rehoboth
  • Construction Begins: Autumn 2021
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $2,862,909.00
    District: District 5

    Contracts (2) Progress
    # 116248 -- Construction Contract
    Bridge Replacement Br. No. R-04-004 (Pre-Stressed Concrete Deck Beams) Reed Street over Palmer River 100% Complete
    # 77872 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/10/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 09/04/2021
    Project Management
    100% Design 100% Package Received 07/14/2020
    25% Design 25% Package Received 08/12/2019
    25% Design Design Public Hearing 01/16/2020
    75% Design 75% Package Received 02/25/2020
    Final Design PS&E Received 11/30/2020
    Final Design PS&E Received - Resub 1 01/19/2021
    Final Design PS&E Received - Resub 2 01/27/2021
    Consultant Contract Process Scope to DE 08/14/2017