Project Description:
FALL RIVER- BRIDGE REPLACEMENT, F-02-019, WEAVER STREET OVER MASSACHUSETTS COASTAL RAILROAD
Location:
  • City of Fall River
  • Construction Begins: Summer 2021
    Resident Engineer: Rajat Gogoi
    Construction Bid Price: $5,555,555.00
    District: District 5
    Current Status: Completed West abutment and retaining q walls. Continued installing SOE for the East abutment and retaining walls footings. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place. (as of 04/28/2023)

    Contracts (2) Progress
    # 114902 -- Construction Contract
    Bridge Replacement Br. No. F-02-019 (Pre-Stressed Concrete Deck Beams) Weaver Street over Massachusetts Coastal Railroad 63% Complete
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/17/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Completed West abutment and retaining q walls. Continued installing SOE for the East abutment and retaining walls footings. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 06/19/2021
    Project Management
    100% Design 100% Package Received 01/22/2021
    100% Design 100% Package Comments to DE 02/25/2021
    25% Design 25% Package Received 08/15/2019
    25% Design Design Public Hearing 06/18/2020
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Comments to DE 09/10/2020
    Final Design PS&E Received 04/09/2021
    Final Design PS&E Received - Resub 1 05/04/2021