Project Description:
FALL RIVER- BRIDGE REPLACEMENT, F-02-019, WEAVER STREET OVER MASSACHUSETTS COASTAL RAILROAD
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2021
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $6,284,851.25
    Estimated Total Federal Participating Construction Cost: $6,742,741.50
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 06/19/2021 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: FALL RIVER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $5,569,898.40
    State Cost: $1,392,474.60
    Total Cost: $6,962,373.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 06/19/2021
    Project Management
    100% Design 100% Package Received 01/22/2021
    100% Design 100% Package Comments to DE 02/25/2021
    25% Design 25% Package Received 08/15/2019
    25% Design Design Public Hearing 06/18/2020
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Comments to DE 09/10/2020
    Final Design PS&E Received 04/09/2021
    Final Design PS&E Received - Resub 1 05/04/2021