Project Description:
FALL RIVER- BRIDGE REPLACEMENT, F-02-019, WEAVER STREET OVER MASSACHUSETTS COASTAL RAILROAD
Location:
  • City of Fall River
  • Construction Begins: Summer 2021
    Resident Engineer: Rajat Gogoi
    Construction Bid Price: $5,555,555.00
    District: District 5
    Current Status: Surface course paving is tentatively scheduled for May 1st & 2nd, 2024 depending on weather. Pavement markings tentatively scheduled for May 7, 2024, weather dependent. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place. (as of 04/10/2024)

    Contracts (2) Progress
    # 114902 -- Construction Contract
    Bridge Replacement Br. No. F-02-019 (Pre-Stressed Concrete Deck Beams) Weaver Street over Massachusetts Coastal Railroad 98% Complete
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/17/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Surface course paving is tentatively scheduled for May 1st & 2nd, 2024 depending on weather. Pavement markings tentatively scheduled for May 7, 2024, weather dependent. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Roadway closed to traffic. Detour in place.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 06/19/2021
    Project Management
    100% Design 100% Package Received 01/22/2021
    100% Design 100% Package Comments to DE 02/25/2021
    25% Design 25% Package Received 08/15/2019
    25% Design Design Public Hearing 06/18/2020
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Comments to DE 09/10/2020
    Final Design PS&E Received 04/09/2021
    Final Design PS&E Received - Resub 1 05/04/2021