Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ANDOVER- TEWKSBURY- HIGHWAY LIGHTING SYSTEM REHABILITATION AND REPAIR AT THE INTERCHANGE OF INTERSTATE ROUTES 93 AND 495
Location:
  • Town of Andover
  • Construction Begins: Spring 2021
    Resident Engineer: Ahmad Rafieizadeh
    Construction Bid Price: $4,256,068.00
    District: District 4
    Current Status: Coviello Electric, the General Contractor on setting up for ramp closures on I-495 and I-93 intersection and/or traffic lane closures on I-495 northbound and I-93 northbound and southbound, at 8:00 PM and picking them up before 5:00 AM, starting Sunday Nights until Friday 5:00 AM. The General Contractor has also been removing the old abandoned light poles and pulling out the old wires feeding the old abandoned light poles. Also, the General Contractor has been delivering the light poles and high mast towers from lay down area to the location of installation and assembling the light pole and high mast towers; and installing them. (as of 07/14/2023)

    Contracts (2) Progress
    # 100889 -- Design -- Traffic Signing/Signals
    Work will consist of preparation of plans, specifications, and estimates for the replacement and upgrading of traffic signs and support structures on specific Interstate, US, Final
    # 114226 -- Construction Contract
    Highway Lighting Repairs and Improvements at the Interchange of Interstates 93 and 495 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/09/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 03/27/2021
    Project Management
    100% Design 100% Package Received 01/11/2021
    25% Design 25% Package Received 11/15/2019
    25% Design 25% Package Comments to DE 01/21/2020
    25% Design 25% Package Approved 03/06/2020
    75% Design 75% Package Received 06/25/2020
    75% Design 75% Package Comments to DE 08/14/2020
    Final Design PS&E Received 02/22/2021
    Final Design PS&E to FAPRO 03/01/2021