Project Description:
WESTHAMPTON- BRIDGE REPLACEMENT, W-27-005, KINGS HIGHWAY OVER N BRANCH MANHAN RIVER
Location:
  • Town of Westhampton
  • Construction Begins: Summer 2020
    Resident Engineer: Joseph Gadbois
    Construction Bid Price: $2,142,032.39
    District: District 2

    Contracts (4) Progress
    # 111716 -- Construction Contract
    Bridge Replacement Br. No. W-27-005 (NEXT F Beams) Kings Highway over the North Branch Manhan River Completed
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/31/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 06/27/2020
    Project Management
    100% Design 100% Package Received 04/06/2020
    25% Design 25% Package Received 11/08/2018
    25% Design 25% Package Received - Resub 1 04/01/2019
    25% Design Design Public Hearing 06/27/2019
    75% Design 75% Package Received 11/12/2019
    75% Design 75% Package Received 04/06/2020
    75% Design 75% Package Comments to DE 12/20/2019
    Final Design PS&E Received 06/08/2020
    Final Design PS&E to FAPRO 06/15/2020