DEERFIELD- BRIDGE REPLACEMENT, D-06-001, UPPER ROAD OVER DEERFIELD RIVER
The purpose of this project is to replace the bridge carrying Upper Road over the Deerfield River. The work includes footings, piers, abutments, superstructure, deck, bridge rail, guardrail, approach roadway, and impacted utilities (overhead and underground). The work also includes reconstruction of the intersection of Upper Road and Lower Road due to grade differential with proposed roadway profile.
Location:
  • Town of Deerfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Christopher I Cameron
    Estimated Total Contract Cost: $24,368,779.02
    Estimated Total Federal Participating Construction Cost: $25,508,894.24
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: 100% Package Received (as of 03/05/2024 )

    Contracts (2) Progress
    # 102483 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: DEERFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $17,715,690.40
    State Cost: $4,428,922.60
    Total Cost: $22,144,613.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2016
    Project Initiation Form PIF Entered 06/07/2016
    Project Initiation Form PRC Submitted 06/07/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Management
    100% Design 100% Package Received 03/05/2024
    25% Design 25% Package Received 07/23/2021
    75% Design 75% Package Received 08/07/2023
    75% Design 75% Package Comments to DE 11/13/2023