LENOX- SUPERSTRUCTURE REPLACEMENT, L-07-006, ROARING BROOK ROAD OVER ROARING BROOK
This municipally owned, structurally deficient, two-lane bridge consists of single span steel beams and concrete deck. It was originally constructed in 1939. It has a curb-to-curb width of 24 ft and a span of 32.8 ft. The bridge is currently posted at 18/23/35 tons. Traffic volume data from 2007 indicates an average daily traffic of 100 vehicles per day. If the current bridge were to be closed, current NBI data indicates a 6 mile, un-maintained detour would be the alternate route. The proposed project consists of complete bridge replacement.
Location:
  • Town of Lenox
  • Construction Begins: Autumn 2021
    Resident Engineer: Richard Miskinis Jr
    Construction Bid Price: $1,168,236.00
    District: District 1

    Contracts (3) Progress
    # 116246 -- Construction Contract
    Bridge Superstructure Replacement and Related Work Br. No. L-07-006 (Steel) Roaring Brook Road over Roaring Brook Completed
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77873 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/01/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 09/04/2021
    Project Management
    100% Design 100% Package Received 12/23/2020
    100% Design 100% Package Comments to DE 01/06/2021
    100% Design 100% Package Comments to DE 01/28/2021
    25% Design 25% Package Received 01/17/2020
    25% Design 25% Package Received - Resub 1 04/29/2020
    25% Design Design Public Hearing 06/11/2020
    75% Design 75% Package Received 09/03/2020
    75% Design 75% Package Comments to DE 11/04/2020
    Final Design PS&E Received 03/05/2021
    Final Design PS&E to FAPRO 08/16/2021
    Consultant Contract Process Scope to DE 08/23/2017
    Consultant Contract Process NTP Issued 10/25/2017
    Consultant Contract Process Workhours Approved 09/28/2017