Project Description:
NEW MARLBOROUGH- SUPERSTRUCURE REPLACEMENT OF THREE (3) BRIDGES, N-08-001, NORFOLK ROAD, N-08-017, LUMBERT ROAD, N-08-018, CANAAN-SOUTHFIELD ROAD OVER UMPACHENE RIVER
The proposed project consists of the rehabilitation of three municipally owned, structurally deficient, bridges carrying traffic over the Umpachene River. The superstructures for each bridge will be replaced and the substructures will be modified. The new superstructures will consist of steel beams with composite reinforced concrete decks, installed as Prefabricated Bridge Units (PBUs). The bridge substructures will be modified with precast abutment caps and precast approach slabs. Bridge N-08-017 will be widened to match the approach roadway width. The proposed approach roadway work includes profile modifications, milling and overlay of existing asphalt roadway pavement, full-depth roadway reconstruction, hot mix asphalt paving, installation of guardrail, and pavement markings. The bridges will be closed sequentially during construction and traffic will be detoured.
Location:
  • Town of New Marlborough
  • Construction Begins: Summer 2021
    Resident Engineer: Nicholas Gray
    Construction Bid Price: $2,884,192.50
    District: District 1

    Contracts (2) Progress
    # 114578 -- Construction Contract
    Bridge Superstructure Replacement and Related Work on 3 Bridges Br. Nos. N-08-001, N-08-017 & N-08-018 Norfolk, Lumbert Cross and Canaan Southfield Roads over the Umpachene Ri Completed
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/16/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 05/15/2021
    Project Management
    100% Design 100% Package Received 07/24/2020
    100% Design 100% Package Comments to DE 09/22/2020
    25% Design 25% Package Received 07/09/2018
    25% Design 25% Package Received - Resub 1 09/17/2019
    25% Design Design Public Hearing 06/19/2019
    75% Design 75% Package Received 03/06/2020
    75% Design 75% Package Received 03/30/2020
    Final Design PS&E Received 04/08/2021
    Final Design PS&E to FAPRO 05/03/2021
    Consultant Contract Process Scope to DE 02/27/2017
    Consultant Contract Process NTP Issued 04/06/2017
    Consultant Contract Process Workhours Approved 03/23/2017