Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, C-05-037, WEST OXBOW ROAD OVER WILDER BROOK
This municipally owned, one-lane bridge consists of single span steel beams with concrete deck. It was originally constructed in 1940, but is currently closed to traffic. A temporary bridge is in place. The original bridge had a curb-to-curb width of 14 ft and a span of 37 ft. Traffic volume data from 2007 indicates an average daily traffic of 100 vehicles per day. If the temporary bridge were to be closed, NBI data indicates a 3.6 mile detour would be the alternate route. The proposed project consists of complete bridge replacement.
Location:
  • Town of Charlemont
  • Construction Begins: Summer 2020
    Resident Engineer: Cathy Spaniol
    Construction Bid Price: $1,554,659.50
    District: District 1

    Contracts (2) Progress
    # 110858 -- Construction Contract
    Bridge Replacement Br. No. C-05-037 (NEXT D Beams) West Oxbow Road over Wilder Brook Completed
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/03/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 02/22/2020
    Project Management
    100% Design 100% Package Received 11/01/2019
    25% Design 25% Package Received 06/04/2018
    25% Design 25% Package Comments to DE 10/04/2018
    25% Design Design Public Hearing 03/28/2019
    75% Design 75% Package Received 06/12/2019
    Final Design PS&E Received 01/13/2020
    Final Design PS&E to FAPRO 01/27/2020
    Final Design PS&E Received - Resub 1 03/06/2020