Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, C-05-008, TOWER ROAD OVER CHICKLEY RIVER
This municipally owned, one-lane bridge consists of single span steel beams with open grate deck. It was originally constructed in 1939, but is currently closed to traffic. The original bridge had a curb-to-curb width of 14 ft and a span of 71 ft. Traffic volume data from 2011 indicates an average daily traffic of 100 vehicles per day. Current NBI data indicates a 3 mile detour is the alternate route. The proposed project consists of complete bridge replacement.
Location:
  • Town of Charlemont
  • Construction Begins: Autumn 2020
    Resident Engineer: Darin Aitken
    Construction Bid Price: $4,267,838.39
    District: District 1

    Contracts (3) Progress
    # 111718 -- Construction Contract
    Bridge Replacement Br. No. C-05-008 (Steel) Tower Road over the Chickley River Completed
    # 115772 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77869 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/24/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 06/27/2020
    Project Management
    100% Design 100% Package Received 02/13/2020
    25% Design 25% Package Received 11/05/2018
    25% Design 25% Package Received - Resub 1 04/05/2019
    25% Design Design Public Hearing 08/15/2019
    75% Design 75% Package Received 11/22/2019
    Final Design PS&E Received 05/08/2020
    Final Design PS&E to FAPRO 06/12/2020