Project Description:
NEW MARLBOROUGH- SUPERSTRUCTURE REPLACEMENT, N-08-006, CAMPBELL FALLS ROAD OVER WHITING RIVER
Work under this project consists of the bridge reconstruction/rehabilitation of the bridge structure that was constructed in 1938. The roadway surface, bridge railings, concrete deck and steel beams for each bridge will be replaced as well as the abutment backwall and bridge seat. The new structures will consist of steel beams with composite reinforced concrete decks. The 42’ long single span Campbell Falls Road bridge will increase the width of the existing bridge to 16’ curb to curb roadway width to match the approaches, and will consist of a single 16’ shared travel lane. The existing abutments will be reused with modifications. The bridge will be closed during construction and traffic will be detoured. Proposed approach roadway work for approximately 175feet on the west approach and 150 feet on the east approach of the bridge includes gravel and regrading and the construction of full depth asphalt pavement and roadway resurfacing for 50’ on either side of the bridge. There will be no sidewalks on the proposed bridge or approach roadway.
Location:
  • Town of New Marlborough
  • Construction Begins: Summer 2020
    Resident Engineer: Kevin Moriarty
    Construction Bid Price: $988,356.54
    District: District 1

    Contracts (2) Progress
    # 111199 -- Construction Contract
    Bridge Superstructure Replacement Br. No. N-08-006 Campbell Falls Road over the Whiting River Completed
    # 77845 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/18/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 04/18/2020
    Project Management
    100% Design 100% Package Received 02/28/2020
    25% Design 25% Package Received 10/18/2018
    25% Design Design Public Hearing 08/28/2019
    75% Design 75% Package Received 10/29/2019
    Final Design PS&E Received 02/28/2020
    Final Design PS&E to FAPRO 04/07/2020
    Consultant Contract Process Scope to DE 02/27/2017
    Consultant Contract Process NTP Issued 06/28/2017
    Consultant Contract Process Workhours Approved 06/05/2017