Project Description:
TYRINGHAM- BRIDGE REPLACEMENT, T-10-007, MONTEREY ROAD OVER HOP BROOK
This municipally owned, structurally deficient, two-lane bridge consists of single span steel beams with concrete deck. It was originally constructed in 1939. The bridge has a curb-to-curb width of 26 ft and a span of 26 ft. Traffic volume data from 2010 indicates an average daily traffic of 300 vehicles per day. If the current bridge were to be closed, current NBI data indicates a 3 mile detour would be the alternate route. The proposed project consists of complete bridge replacement.
Location:
  • Town of Tyringham
  • Construction Begins: Summer 2020
    Resident Engineer: Richard Miskinis Jr
    Construction Bid Price: $1,634,603.14
    District: District 1

    Contracts (2) Progress
    # 111058 -- Construction Contract
    Bridge Replacement Br. No. T-10-007 Monterey Road over Hop Brook Completed
    # 77855 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/10/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 03/21/2020
    Project Management
    100% Design 100% Package Received 10/15/2019
    25% Design 25% Package Received 04/19/2018
    25% Design Design Public Hearing 11/01/2018
    75% Design 75% Package Received 02/28/2019
    75% Design 75% Package Comments to DE 06/28/2019
    Final Design PS&E Received 01/09/2020
    Final Design PS&E to FAPRO 03/09/2020
    Consultant Contract Process Scope to DE 02/27/2017
    Consultant Contract Process NTP Issued 05/10/2017
    Consultant Contract Process Workhours Approved 04/25/2017