SAVOY- BRIDGE SUPERSTRUCTURE REPLACEMENT, S-06-003, CENTER ROAD OVER CENTER BROOK
This municipally owned, structurally deficient, two-lane bridge consists of single span steel beams with concrete deck. It was originally constructed in 1938. The bridge has a curb-to-curb width of 20 ft and a span of 26.9 ft. The bridge is currently reduced in width and posted with a weight restriction. Traffic volume data from 2007 indicates an average daily traffic of 300 vehicles per day. If the current bridge were to be closed, current NBI data indicates a 1.8 mile detour would be the alternate route. The proposed project consists of complete bridge replacement.
Location:
  • Town of Savoy
  • Construction Begins: Autumn 2021
    Resident Engineer: Christopher Pompi
    Construction Bid Price: $1,520,676.00
    District: District 1

    Contracts (2) Progress
    # 116251 -- Construction Contract
    Bridge Superstructure Replacement and Related Work Br. No. S-06-003 (Pre-Stressed Concrete Deck Beams) Center Road over Center Brook Completed
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/18/2021
    Contract Information
    Project Designer:
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2016
    Project Initiation Form PIF Entered 06/08/2016
    Project Initiation Form PRC Submitted 06/08/2016
    Project Review Committee PRC Approved 09/20/2016
    Project Status Advertised 09/04/2021
    Project Management
    100% Design 100% Package Received 03/05/2021
    100% Design 100% Package Comments to DE 04/05/2021
    25% Design 25% Package Received 12/18/2019
    25% Design 25% Package Comments to DE 01/21/2020
    25% Design 25% Package Rejected 02/14/2020
    25% Design 25% Package Received - Resub 1 06/25/2020
    25% Design Design Public Hearing 09/30/2020
    75% Design 75% Package Received 12/14/2020
    75% Design 75% Package Comments to DE 01/11/2021
    Final Design PS&E Received 04/30/2021
    Final Design PS&E Received - Resub 1 06/04/2021
    Final Design PS&E Received - Resub 2 06/24/2021