Project Description:
LUNENBURG- BRIDGE REHABILITATION, L-17-009, ROUTE 2A OVER PEARL HILL BROOK
The bridge rehabilitation will consist of two construction stages to replace the existing hybrid superstructure with a new precast concrete deck and HMA overlay. There will also be safety upgrades consisting of new parapets/endposts/guardrail. A cantilevered support for sidewalk/utilities may also be required.
Location:
  • Town of Lunenburg
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Hassan Valipour
    Construction Bid Price: $1,413,607.00
    District: District 3

    Contracts (4) Progress
    # 113595 -- Construction Contract
    Bridge Rehabilitation Br. No. L-17-009 (Concrete) Massachusetts Avenue (Route 2A) over Pearl Hill Brook Completed
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/26/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/28/2016
    Project Initiation Form PIF Entered 06/28/2016
    Project Initiation Form PRC Submitted 06/28/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 12/05/2020
    Project Management
    100% Design 100% Package Received 12/12/2019
    100% Design 100% Package Comments to DE 02/12/2020
    25% Design 25% Package Received 06/05/2018
    25% Design 25% Package Comments to DE 08/22/2018
    25% Design 25% Package Approved 11/30/2018
    25% Design Design Public Hearing 06/20/2019
    75% Design 75% Package Received 07/15/2019
    75% Design 75% Package Comments to DE 09/13/2019
    Final Design PS&E Received 05/04/2020
    Final Design PS&E to FAPRO 11/23/2020