Project Description:
BOSTON- SIDEWALKS, WHEELCHAIR RAMP & CROSSWALKS REPAIRS AT VARIOUS CA/T LOCATIONS (CRC 25) CONTRACT 2
Scope for this project includes investigation, inventory of deficiencies, design, bidding, construction, and administration to repair defective sidewalks, crosswalks, and pedestrian ramps previously constructed under the CA/T Project. The implementation of these repairs will require careful coordination with MassDOT and the City of Boston (and other consultants as needed), as the scope requires the ultimate step to include turnover of these assets to the City of Boston. In addition, the scope includes careful coordination with MassDOT's ongoing project 607020 "ADA Improvements and Upgrades to Various Locations". The great majority of these elements – the downtown section - were included in the C17A6 contract, which was the last major construction contract. In addition there were sidewalk sections installed in the South Bay Area (C09C2), South Boston (C01A6), and East Boston. It should be noted that the turnover of the East Boston sidewalks, since they were to be owned by Massport and not the City of Boston, followed a separate process.
Location:
  • City of Boston
  • Construction Begins: Summer 2017
    Resident Engineer: Noah Woldemariam
    Construction Bid Price: $7,164,303.50
    District: District 6

    Contracts (3) Progress
    # 100596 -- Construction Contract
    Sidewalk, Wheelchair Ramp and Crosswalk Repairs and Improvements at Various CA/T Locations (CRC 25) Completed
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/12/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2014
    Project Initiation Form PIF Entered 07/01/2016
    Project Initiation Form PRC Submitted 11/01/2016
    Project Review Committee PRC Approved 11/29/2016
    Project Status Advertised 06/03/2017
    Project Management
    Final Design PS&E Received 02/27/2017
    Final Design PS&E to FAPRO 05/19/2017