| Project Description: |
LENOX- INTERSECTION SAFETY IMPROVEMENTS AT ROUTE 7/20 AND HOUSATONIC STREET (PHASE I)
This project proposes safety improvements at this intersection; which is currently identified as a 2011-2013 HSIP cluster. Proposed work includes lengthening auxiliary turn lanes, implementing minor geometric improvements, and upgrading traffic signs and markings. Traffic signal improvements are proposed for Phase II in a future year.
|
| Location: |
|
| Construction Begins: | Winter 2017/2018 |
| Resident Engineer: | Jiang Liang![]() |
| Construction Bid Price: | $218,907.00 |
| District: | District 1 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||