Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- BRIDGE DRAINAGE INSTALLATION & REHABILITATION AT VARIOUS LOCATIONS
Work consists of bridge drainage installation and rehabilitation at various locations in the District.
Location:
Construction Begins: Summer 2018
Resident Engineer: Eric Mistretta
Construction Bid Price: $1,516,740.00
District: District 6

Contracts (1) Progress
# 102464 -- Construction Contract
Bridge Drainage Repairs and Improvements at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/16/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/01/2016
    Project Initiation Form PIF Entered 08/01/2016
    Project Initiation Form PRC Submitted 09/06/2016
    Project Review Committee PRC Approved 09/06/2016
    Project Status Advertised 10/07/2017
    Project Management
    100% Design 100% Package Received 08/11/2017
    Final Design PS&E Received 09/06/2017
    Final Design PS&E to FAPRO 10/02/2017