Project Description:
WILMINGTON- BRIDGE REPLACEMENT, W-38-029 (2KV), ST 129 LOWELL STREET OVER I 93
The scope of work will include a total bridge replacement. The deck is structurally deficient. The superstructure has a low clearance of 14'-3" over I-93. A bridge replacement will allow adequate clearance over the interstate highway.
Location:
  • Town of Wilmington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Eamon Kernan
    Estimated Total Contract Cost: $22,079,622.85
    Estimated Total Federal Participating Construction Cost: $25,500,182.58
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 03/04/3034 )

    Contracts (1) Progress
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WILMINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $16,592,888 (NHPP - Penalty)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $13,274,310.40
    State Cost: $3,318,577.60
    Total Cost: $16,592,888.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/12/2016
    Project Initiation Form PIF Entered 08/12/2016
    Project Initiation Form PRC Submitted 08/12/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management
    25% Design 25% Package Received 05/30/2024
    Consultant Contract Process NTP Issued 03/04/3034