Project Description:
WILMINGTON- BRIDGE REPLACEMENT, W-38-029 (2KV), ST 129 LOWELL STREET OVER I 93
The scope of work will include a total bridge replacement. The deck is structurally deficient. The superstructure has a low clearance of 14'-3" over I-93. A bridge replacement will allow adequate clearance over the interstate highway.
Location:
  • Town of Wilmington
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Eamon Kernan
    Estimated Total Contract Cost: $24,692,936.23
    Estimated Total Federal Participating Construction Cost: $28,276,158.35
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 03/04/3034 )

    Contracts (1) Progress
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WILMINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $12,763,760.00
    State Cost: $3,190,940.00
    Total Cost: $15,954,700.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/12/2016
    Project Initiation Form PIF Entered 08/12/2016
    Project Initiation Form PRC Submitted 08/12/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management
    25% Design 25% Package Received 05/30/2024
    25% Design Design Public Hearing 09/18/2024
    75% Design 75% Package Received 12/03/2024
    Consultant Contract Process NTP Issued 03/04/3034