Project Description:
QUINCY- RECONSTRUCTION OF SEA STREET
Project will improve safety, reduce congestion, upgrade traffic signals and roadway conditions for all users: vehicles, transit, bike and pedestrian.
Location:
  • City of Quincy
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2023
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $11,023,858.00
    Estimated Total Federal Participating Construction Cost: $11,612,978.20
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 100% Package Received (as of 03/09/2023 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,133,310.40
    State Cost: $2,033,327.60
    Total Cost: $10,166,638.00

    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/22/2016
    Project Initiation Form PIF Entered 09/30/2016
    Project Initiation Form PRC Submitted 09/30/2016
    Project Review Committee PRC Approved 10/14/2016
    Project Management
    100% Design 100% Package Received 03/09/2023
    100% Design 100% Package Comments to DE 02/06/2023
    25% Design 25% Package Received 02/07/2017
    25% Design Design Public Hearing 12/05/2019
    75% Design 75% Package Received 09/09/2021
    75% Design 75% Package Comments to DE 12/13/2021