QUINCY- RECONSTRUCTION OF SEA STREET
Project will improve safety, reduce congestion, upgrade traffic signals and roadway conditions for all users: vehicles, transit, bike and pedestrian.
Location:
  • City of Quincy
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2023
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $9,475,312.06
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 75% Package Received (as of 09/09/2021 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; STBG+TAP Total Cost = $5,843,442; MPO Evaluation Score = 40; TAP Project Proponent = Quincy
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,493,750.40
    State Cost: $1,123,437.60
    Total Cost: $5,617,188.00

    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; STBG+TAP Total Cost = $5,843,442; MPO Evaluation Score = 40; TAP Project Proponent = Quincy
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $181,003.20
    State Cost: $45,250.80
    Total Cost: $226,254.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/22/2016
    Project Initiation Form PIF Entered 09/30/2016
    Project Initiation Form PRC Submitted 09/30/2016
    Project Review Committee PRC Approved 10/14/2016
    Project Management
    25% Design 25% Package Received 02/07/2017
    25% Design Design Public Hearing 12/05/2019
    75% Design 75% Package Received 09/09/2021