Project Description:
SPRINGFIELD- RECONSTRUCTION OF SUMNER AVENUE AT DICKINSON STREET AND BELMONT AVENUE (THE "X")
The project includes reconstruction of The "X" intersection in Springfield. The project includes reconstruction of the existing roadways, realignment of critical intersections, and implementation of mini-roundabouts to improve traffic flow through non critical intersections. Pedestrian, bicycle, and transit accommodations will be improved to provide safe and healthy transportation alternatives. In addition to improved safety, the area will be improved by streetscaping, landscaping, drainage and utility improvements, and accessibility/connectivity improvements. Multi-Use paths will connect the surrounding neighborhood to Forest Park via Cliftwood St and Trafton St on the eastern border of the park. The Multi-Use trail contains two 5’ opposing lanes and entrance protection to prevent prohibited motor vehicles from entering.
Location:
  • City of Springfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $26,711,831.10
    Estimated Total Federal Participating Construction Cost: $26,269,004.55
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 08/31/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/31/2016
    Project Initiation Form PIF Entered 08/31/2016
    Project Initiation Form PRC Submitted 09/16/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 08/31/2024
    Project Management
    100% Design 100% Package Received 05/08/2023
    100% Design 100% Package Comments to DE 06/22/2023
    25% Design 25% Package Received 05/25/2018
    25% Design Design Public Hearing 09/17/2019
    75% Design 75% Package Received 01/19/2022
    75% Design 75% Package Comments to DE 04/21/2022
    Final Design PS&E Received 04/22/2024
    Final Design PS&E Received - Resub 1 06/04/2024
    Final Design PS&E Received - Resub 2 06/20/2024
    Final Design PS&E Received - Resub 3 07/29/2024