Project Description:
AMHERST- BELCHERTOWN- NORWOTTUCK RAIL TRAIL RESURFACING, FROM STATION ROAD IN AMHERST TO WARREN WRIGHT ROAD IN BELCHERTOWN (1.5 MILES)
The purpose is to resurface and rehabilitate a 1.5 mile segment of the MCRT – Norwottuck Rail Trail. The paved surface was originally constructed in 1997. The pavement surface is cracked and deteriorating in many places and reaching the end of its planned life. There are also several root-damaged areas and edge drop-offs which pose significant safety concerns for cyclists and pedestrians. Improvement to the Warren Wright Parking Area is also planned.
Location:
  • Town of Amherst
  • Town of Belchertown
  • Construction Begins: Autumn 2022
    Resident Engineer: Peng Xu
    Construction Bid Price: $1,296,409.01
    District: District 2

    Contracts (4) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 119676 -- Construction Contract
    Resurfacing and Related Work on a Section of the Norwottuck Rail Trail Completed
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/28/2022
    Contract Information
    Project Designer: Other
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/31/2016
    Project Initiation Form PIF Entered 08/31/2016
    Project Initiation Form PRC Submitted 09/16/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 08/06/2022
    Project Management
    100% Design 100% Package Received 01/19/2022
    100% Design 100% Package Comments to DE 03/04/2022
    25% Design 25% Package Received 10/09/2020
    25% Design 25% Package Comments to DE 12/15/2020
    25% Design Design Public Hearing 11/18/2021
    75% Design 75% Package Received 01/19/2022
    Final Design PS&E Received 06/21/2022
    Final Design PS&E Received - Resub 1 07/18/2022
    Consultant Contract Process NTP Issued 02/28/2020