Project Description:
HOLDEN- WEARING SURFACE PRESERVATION AND RELATED REPAIRS TO H-18-027, MALDEN STREET OVER I-190 (NB AND SB)
The work on the subject bridge will consist of removing (hydro demolition) the existing wearing surface, repairing the deck and installing a thin rigid overlay (LMC or Dense concrete) and all related work.
Location:
Construction Begins: Spring 2018
Resident Engineer: Wayne Richard
Construction Bid Price: $1,527,601.00
District: District 3

Contracts (1) Progress
# 102554 -- Construction Contract
Bridge Deck, Joint and Substructure Repairs and Related Work (Including Painting) Br. No. H-18-027 Malden Street over Interstate 190. Completed

Bridges

Contract Dates
Notice to Proceed: 06/13/2018
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 08/31/2016
Project Initiation Form PIF Entered 08/31/2016
Project Initiation Form PRC Submitted 08/31/2016
Project Review Committee PRC Approved 08/31/2016
Project Status Advertised 10/21/2017
Project Management
Final Design PS&E Received 08/30/2017
Final Design PS&E to FAPRO 09/26/2017