BOSTON- FORT POINT CHANNEL WATER TRANSPORTATION FACILITY CONSTRUCTION
This project replaces 607318 since the construction contract was terminated. The Fort Point Channel Ferry Facility (FPCFF) is a CA/T Project mitigation measure required to support development of Bostonís water transport system. The FPCFF is to provide ADA-accessible, public ferry service and public landing benefits for the westerly side of the Fort Point Channel. The project has been delayed for a variety of reasons, until recently because of conflicts with adjacent Transitway and private construction activities along with the Old Northern Avenue Bridge (ONA Bridge). The construction of this project is complex due to low clearance under the bridges along the channel and operational constraints. The project consists of the construction of a fixed timber and steel multi-level deck and a floating barge system with ADA compliant ramps.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2023
    Project Manager: Carrie Lavallee
    Estimated Total Contract Cost: $3,639,861.04
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: PS&E Received - Resub 3 (as of 04/17/2018 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/21/2016
    Project Initiation Form PIF Entered 09/21/2016
    Project Initiation Form PRC Submitted 09/21/2016
    Project Review Committee PRC Approved 09/21/2016
    Project Management
    Final Design PS&E Received 09/09/2016
    Final Design PS&E Received - Resub 1 12/12/2016
    Final Design PS&E Received - Resub 2 05/17/2017
    Final Design PS&E Received - Resub 3 04/17/2018