Project Description:
PROVINCETOWN- CORRIDOR IMPROVEMENTS AND RELATED WORK ON SHANK PAINTER ROAD, FROM ROUTE 6 TO BRADFORD STREET
Work on this project consists of roadway reconstruction, sidewalk construction and reconstruction, drainage upgrades, pavement markings and signs along Shank Painter Road. Geometric improvements are proposed at the Route 6/Shank Painter Road intersection. Also included in the project is a road diet on Route 6 from Shank Painter Road to the National Seashore, which will allow for improved bicycle and pedestrian accommodation in the form of a shared use path.
Location:
  • Town of Provincetown
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $18,916,555.31
    Estimated Total Federal Participating Construction Cost: $16,955,470.22
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 04/10/2024 )

    Contracts (1) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Other Federal Aid
    Federal Cost: $376,000.00
    State Cost: $94,000.00
    Total Cost: $470,000.00

    Planned Federal FY: 2026
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $800,000.00
    State Cost: $200,000.00
    Total Cost: $1,000,000.00

    Planned Federal FY: 2026
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $160,000.00
    State Cost: $40,000.00
    Total Cost: $200,000.00

    Planned Federal FY: 2026
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,420,778.40
    State Cost: $605,194.60
    Total Cost: $3,025,973.00

    Planned Federal FY: 2027
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $640,000.00
    State Cost: $160,000.00
    Total Cost: $800,000.00

    Planned Federal FY: 2027
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,401,628.00
    State Cost: $600,407.00
    Total Cost: $3,002,035.00

    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,211,941.60
    State Cost: $802,985.40
    Total Cost: $4,014,927.00

    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Municipality is TAP Proponent; AC 2026-2027; CMAQ approved; TFPC $12,876,806; Funding CMAQ - $5,800,000; STBG - $5,591,879; TAP - $1,014,927; FLAP - $470k (Statewide, 100% FA)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,849,396.80
    State Cost: $962,349.20
    Total Cost: $4,811,746.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/23/2016
    Project Initiation Form PIF Entered 02/21/2017
    Project Initiation Form PRC Submitted 02/22/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Management
    25% Design 25% Package Received 02/07/2020
    25% Design 25% Package Comments to DE 03/25/2021
    25% Design Design Public Hearing 06/13/2023
    75% Design 75% Package Received 04/10/2024
    Consultant Contract Process NTP Issued 08/10/2016