Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY REPAIR & MAINTENANCE OF HVAC SYSTEMS VARIOUS LOCATIONS
The purpose of the contract is to provide technical, mechanical and software assistance and repairs, as directed, with the HVAC systems and automation controls at MassDOT Facilities within the MHS roadway system.
Location:
Construction Begins: Winter 2017/2018
Resident Engineer: Joseph Colleran
Construction Bid Price: $437,204.00
District: District 6

Contracts (1) Progress
# 100232 -- Construction Contract
Scheduled and Emergency HVAC System Repairs and Improvements at Various Locations. GENERAL BID Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/08/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/28/2016
    Project Initiation Form PIF Entered 11/28/2016
    Project Initiation Form PRC Submitted 11/28/2016
    Project Review Committee PRC Approved 12/05/2016
    Project Status Advertised 04/22/2017
    Project Management
    100% Design 100% Package Received 01/24/2017
    Final Design PS&E Received 04/07/2017
    Final Design PS&E to FAPRO 04/12/2017