NEW BEDFORD- IMPROVEMENTS AT ASHLEY AND LINCOLN ELEMENTARY SCHOOLS (SRTS)
Work will consist of corridor improvements on Ashley Boulevard between Wood Street and Nash Road, including the construction of curb bump-outs, ADA-compliant accessible ramps for perpendicular pedestrian crossings, replacement of MUTCD compliant school zone flashers, and installation of 5-foot bike lanes southbound and "sharrows" northbound.
Location:
  • City of New Bedford
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Matthew Lambert
    Construction Bid Price: $1,333,067.55
    District: District 5

    Contracts (2) Progress
    # 105572 -- Construction Contract
    Sidewalk Reconstruction and Related Work (Including Signals) on a Section of Ashley Boulevard and Adjacent Streets (Safe Routes to School – Ashley and Lincoln Elementary Schoo Completed
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/07/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/02/2016
    Project Initiation Form PIF Entered 12/02/2016
    Project Initiation Form PRC Submitted 12/02/2016
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 08/18/2018
    Project Management
    100% Design 100% Package Received 04/09/2018
    25% Design Design Public Hearing 02/28/2018
    75% Design 75% Package Received 09/06/2017
    75% Design 75% Package Comments to DE 11/28/2017
    Final Design PS&E Received 07/11/2018
    Final Design PS&E to FAPRO 08/06/2018
    Final Design PS&E Received - Resub 1 07/31/2018