Project Description:
TAUNTON- CORRIDOR IMPROVEMENTS AND RELATED WORK ON BROADWAY (ROUTE 138), FROM PURCHASE STREET TO JACKSON STREET (PHASE 2)
The project includes improvements to Broadway (Route 138) for approximately from Purchase Street to Jackson Street. Specifically, the improvements will include full depth roadway reconstruction and pavement resurfacing, drainage improvements, reconstruction of sidewalks with ADA compliant ramps, provision of bicycle accommodations, as well as geometric modifications and upgraded traffic signal systems.
Location:
  • City of Taunton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $10,196,956.00
    Estimated Total Federal Participating Construction Cost: $12,757,583.33
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 09/14/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/27/2016
    Project Initiation Form PIF Entered 02/23/2017
    Project Initiation Form PRC Submitted 03/22/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 09/14/2024
    Project Management
    100% Design 100% Package Received 09/08/2023
    100% Design 100% Package Comments to DE 10/31/2023
    25% Design 25% Package Received 05/14/2021
    25% Design 25% Package Comments to DE 08/24/2021
    25% Design Design Public Hearing 12/14/2022
    75% Design 75% Package Received 05/05/2023
    75% Design 75% Package Comments to DE 06/16/2023
    Final Design PS&E Received 01/26/2024
    Final Design PS&E Received - Resub 1 04/05/2024
    Final Design PS&E Received - Resub 2 04/12/2024
    Final Design PS&E Received - Resub 3 05/14/2024