| Project Description: |
DALTON- INTERSECTION IMPROVEMENTS AT ROUTES 8 & 9 (MAIN ST) AT SOUTH ST & WEST HOUSATONIC ST
Intersection improvements at Routes 8 & 9 (Main Street) at South Street & West Street to improve safety at a 2012-14 HSIP cluster. Upgrades may include traffic signals, signs, pavement markings, geometric modifications, and/or change in intersection control (roundabout). Recommendations from Road Safety Audit will be basis for design.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Jonathan E Freeman![]() |
| Estimated Total Contract Cost: | $1,752,000.00 |
| Estimated Total Federal Participating Construction Cost: | $1,900,325.00 |
| District: | District 1 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 04/18/2018 ) |
|
Bridges |
||||||||
|
|
|
||||||||||||||||||||||||||