BOSTON- INTERSECTION IMPROVEMENTS MORTON STREET (ROUTE 203) AT BLUE HILL AVE, AT COURTLAND ROAD/HAVELOCK STREET, AND AT HARVARD STREET
Intersection improvements at Morton Street at Harvard Street; Morton at Blue Hill Ave; Morton at Courtland Rd & Havelock St to improve safety at a 2012-14 Top 200 crash site. Upgrades may include traffic signals, signs, pavement markings, and/or geometric modifications. Recommendations from Road Safety Audit for the three intersections will be basis for design.
Location:
  • City of Boston
  • Construction Begins: Spring 2020
    Resident Engineer: Patrick Finn
    Construction Bid Price: $2,997,799.20
    District: District 6

    Contracts (2) Progress
    # 109679 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at 2 Locations along Morton Street (Route 203) Completed
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/05/2017
    Project Initiation Form PIF Entered 01/05/2017
    Project Initiation Form PRC Submitted 01/05/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 06/20/2019
    100% Design 100% Package Comments to DE 07/23/2019
    25% Design 25% Package Received 04/10/2018
    25% Design 25% Package Comments to DE 07/17/2018
    25% Design Design Public Hearing 12/19/2018
    75% Design 75% Package Received 02/21/2019
    75% Design 75% Package Comments to DE 03/26/2019
    Final Design PS&E Received 08/26/2019
    Final Design PS&E to FAPRO 08/30/2019