Project Description:
DISTRICT 4- BRIDGE STRUCTURAL REPAIRS AND RELATED WORK AT VARIOUS LOCATIONS ALONG THE I-495 CORRIDOR
Location:
Construction Begins: Autumn 2019
Resident Engineer: Christopher Leahy
Construction Bid Price: $1,895,388.75
District: District 4

Contracts (1) Progress
# 108458 -- Construction Contract
Bridge Structural Repairs and Related Work (Including Painting) along Interstate 495 Completed

Bridges

Contract Dates
Notice to Proceed: 11/01/2019
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 01/10/2017
Project Initiation Form PIF Entered 01/10/2017
Project Initiation Form PRC Submitted 01/10/2017
Project Review Committee PRC Approved 03/23/2017
Project Status Advertised 06/29/2019
Project Management
Final Design PS&E Received 04/16/2019
Final Design PS&E Received - Resub 1 06/18/2019