Project Description:
SWANSEA- TRAFFIC SIGNAL AND SAFETY IMPROVEMENTS AT THREE INTERSECTIONS ON ROUTE 6
Work on this project consists of intersection improvements at the following three intersections: Route 6/Route 118 (Swansea Mall Drive) Route 6/Maple Avenue and Route 6/Route 136 (Market Street). Work includes traffic signal upgrades, geometric improvements, improved bicycle and pedestrian accessibility, signs, pavement markings, and/or geometric modifications. The intent of the project is to address safety at these three high crash location. Recommendations from the Road Safety Audit will be basis for design.
Location:
  • Town of Swansea
  • Construction Begins: Spring 2025
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $14,300,500.00
    District: District 5
    Current Status: The contractor is expected to continue sewer work at the Rte. 6 @ Rte. 18 Location. National Grid is continuing to work on pole relocations at the Maple Ave intersection. Both tasks are expected to continue over the next several weeks. Liberty Utilities has also mobilized and began gas main relocations on Maple Ave. These operations may be impacted by snow/ice events. Normal work hours are Monday through Friday, 7:00AM to 3:30 PM Expect Periodic Lane closures and restrictions. (as of 02/04/2026)

    Contracts (3) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 130047 -- Construction Contract
    Traffic Signal and Safety Improvements at Three Intersections on Route 6 19% Complete
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/17/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/10/2017
    Project Initiation Form PIF Entered 01/10/2017
    Project Initiation Form PRC Submitted 01/10/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 04/19/2025
    Project Management
    100% Design 100% Package Received 03/24/2022
    100% Design 100% Package Comments to DE 06/24/2022
    25% Design 25% Package Received 03/16/2018
    25% Design 25% Package Comments to DE 06/04/2018
    25% Design Design Public Hearing 12/17/2020
    75% Design 75% Package Received 07/15/2021
    75% Design 75% Package Comments to DE 12/20/2021
    Final Design PS&E Received 11/01/2022
    Final Design PS&E Received - Resub 1 08/02/2024
    Final Design PS&E Received - Resub 2 10/15/2024
    Final Design PS&E Received - Resub 3 02/13/2025
    Consultant Contract Process NTP Issued 10/04/2017