Project Description: |
BOSTON- CAMBRIDGE- BRIDGE PRESERVATION OF B-16-246=C-01-029, ELIOT STREET OVER THE CHARLES RIVER
Includes concrete and masonry repairs, new wearing surface and new bridge joints
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2024 |
Project Manager: | Anthony Christakis![]() |
Estimated Total Contract Cost: | $6,706,345.83 |
Estimated Total Federal Participating Construction Cost: | $6,973,936.10 |
District: | District 6 |
Current Status: | PS&E Received (as of 05/22/2023 ) |
|
Bridges
|
|
|
|